Project
Year
Total Cost
per-House*
Alpine Main 2012,13 $�
79,000 $�� 790
New Water Pump 2014 $�
11,000 $�� 110
Complete Paving 2015 $270,000 $2,700
Chip/Seal 2016 $�
56,000 $�� 560
Lagoon Dredge 2016 $�
20,000 $�� 200
Breeder Dredge
2016 $� 55,000 $��
550
Total $491,000 $4,910
��Unless we take some
action, the FC recommends that these
costs be borne through assessments.